THE STATE'S PLAN:
|
THE TIGHT TIMELINEThis was the NJEDA Planned timeline:
14 February 2017 NJEDA Board Meeting to approve architect and construction manager Feb 2017: Phase 1 (Design) - expected to last six months April-June 2017: BUDGET AND BONDS APPROVALS - details coming soon. July-Sept 2017: Bonds issued Sept 2017: Phase II (Pre-construction) Sept 2017- Sept 2019: Construction July 2019-Sept 2019: Demolition DOCUMENTSNJEDA Overview Presentation
21 September 2016 KSS Architects Feasibility Study 15 April 2015 Full document (lower res) Volume 1: includes detailed maps and plans for all the proposed buildings Volume 2 & 3 : includes the financial analysis of the proposed developments. Taxation Building Study 26 August 2013 Lammey & Giorgio, Architects This document looks at the systems in the current Taxation building at State/Barrack Streets and is the basis on which the demo/build-new decision was made. |